Friday, July 2, 2010


I found the final drainage work on main lane complete couple of weeks. Water sump is progressing well and I think should be done by end of July. Monsoon rains helped to pack the roads and loose soil. During my last week's (6/26/10) visit, I found lot of foot traffic from customers checking their villas.
The entry portal work is almost complete. Now the project name is striking at the entrance. Looks good.






-7/3/10