Good, sustained progress. Most villas construction picked up pace. Before the rains start, builder says that he wants to complete the roads and external plasting work.
Heard that all the east facing 325sq yds lots are sold out. I did see quite a bit of customer activity when I visited the site today.
One thing where there is no activity yet, is the Club House.